Skip to content
UtilityRateWatch

Potomac Edison rate increase

Electric · Maryland, West Virginia · Investor-owned utility · part of FirstEnergy Corp.

Proposed

Last checked

In Maryland, Potomac Edison has a request pending with regulators: 2026 Maryland distribution rate request, seeking $52.8 million. See the details below for what the sources say about bill impacts.

Details and sources · Estimate for your home

Rate changes, newest first

2026 Maryland distribution rate request

Base rate case · Maryland · Electric

Proposed

Typical residential bill

Not stated for a specific usage level. Any figures the sources give are in the summary below.

Filed
September 4, 2026
Decision expected
Not disclosed
Requested effective
Not disclosed
Requested increase
$52.8 million
Approved increase
Pending
Docket
Case No. 9904

Potomac Edison asked the Maryland Public Service Commission for a $52.8 million distribution rate increase, which the company says would raise the average residential bill by about 5.3% a month. The PSC (Case No. 9904) set public comment hearings for Dec. 1, 2026 in Cumberland and Dec. 8 online; no decision date has been published.

Utility's stated reasons

  • upgrades to aging infrastructure
  • grid modernization
  • reliability projects such as tree removal and cable replacement
Sources (2) · Based on news or utility announcements

Last verified Nov 16, 2026

West Virginia two-step inflation and investment adjustment (2026-2027)

Multi-year rate plan · West Virginia · Electric

In effect

Typical residential bill (1,000 kWh/month)

  • +$4.00/mostarting August 1, 2026 (+3%)FirstEnergy's rounded figures for Mon Power and Potomac Edison at 1,000 kWh: $142 from August 1, 2026 minus $138 before.
  • +2.9%then from June 1, 2027FirstEnergy gives only the percentage for the second step.

Typical bill before the change: $138.00/month

Filed
May 15, 2026
Decided
July 31, 2026
Effective
August 1, 2026
Requested increase
Not disclosed
Approved increase
$76 million
Docket
26-0508-E-42T

West Virginia regulators approved a two-step increase for Mon Power and Potomac Edison instead of a $188.4 million base rate request: $37.9 million from August 1, 2026 and $37.6 million from June 1, 2027. The average residential bill rises about 3.0%, then 2.9%. The companies agreed not to file a new base rate case before April 1, 2028. PSC staff and the Consumer Advocate opposed it.

Utility's stated reasons

  • capital investment since the last base rate case
  • inflation
  • surcharges rolled into base rates
Sources (2) · Based on news or utility announcements

Last verified Nov 9, 2026

What it could mean for your bill

Sources state the impact for one typical home. Enter your own usage or bill for a rough estimate.

For: West Virginia two-step inflation and investment adjustment (2026-2027) (in effect)

I know my
kWh/month

Enter a number to see a rough estimate for your home.

Who decides

Utility website: www.firstenergycorp.com

Other utilities nearby

Last checked Nov 16, 2026. Spotted something out of date? Tell us.